The Environment Agency is progressing with its plans for the Exmouth tidal defence scheme – the Agency is currently meeting landowners and residents believed to be most affected by the project.
The Environment Agency has been working in collaboration with East Devon District Council since 2015 to develop the scheme and the business case for funding; this culminated in approval of £12 million of government funding in September 2017.
East Devon District Council is also contributing to the project, and will maintain the defences built on council-owned land in the future.
Photo Environment Agency: Exmouth in storm conditions in 2014
Approximately 1,400 residential and 400 commercial properties are at risk from tidal flooding in Exmouth.
Representatives from the project team, the Environment Agency’s contractor Team Van Oord (TVO) and Environment Agency staff will be in and around Exmouth over the coming weeks.
A planning application for the scheme has been submitted to the planning authority East Devon District Council following the completion of investigation works in and around Exmouth.
Apart from a select few sites where some extra survey information is required, the Environment Agency now has detailed information about the site.
The Environment Agency’s contractor, TVO, who are designing and building the project, has been reviewing the GPR results, and is now looking to positively identify exactly what is underground in a number of areas.
The need for a new tidal defence scheme for Exmouth was initially identified as part of a flood risk management strategy for the whole of the Exe Estuary.
Following analysis of possible flood scenarios for today, and in the future, it was recommended that Exmouth’s existing defences should be improved in the short term.
After gathering feedback from local public consultation in 2016, the Environment Agency concluded that flood risk should be reduced from the current 1-in-25-year risk (4% chance of flooding in any year) to 1-in-200-year (0.5% chance).
The impacts of climate change and sea level rise were included in the Environment Agency’s analysis.
Following a review of the outline design and consultation feedback, the Environment Agency believes the best approach is to build improved defences today that can be easily improved again in the future. Analysis showed that the next ‘intervention’ for further flood defence improvements may be needed by the year 2045.
Team Van Oord (TVO) were awarded the design and build contract for the Exmouth tidal defence scheme in October 2017.
The contractors are working on the design, which includes 3 areas – the work will include raising existing flood defences, strengthening the existing seawall and new set-back defences along the landward side of the Esplanade. This will mean that areas of the Esplanade and highway will still be inundated during storms, however flood water will be stopped from flowing down nearby roads by the new defences.
If planning permission is granted this year, the Environment Agency aims to start construction in early 2019. Until the scheme is built, Exmouth remains at a high risk of flooding.
HUBER Technology UK & Ireland are inviting people to register for their March webinar where they will be providing information about HUBER water intake screens for municipal and industrial applications.

Hear how United Utilities is accelerating its investment to reduce spills from storm overflows across the Northwest.