The third year of construction on a £33 million Environment Agency flood defence scheme has been completed, resulting in 2300 properties being better protected.

The Stallingborough flood defence scheme, which began construction in 2023, is working to safeguard homes, nationally important infrastructure, and vital industry in Lincolnshire.
The improved flood defences enable significant economic development in the area. A power station is being built, large areas of land can now be developed, and rail stations and highways have enhanced protection from flooding. It is estimated this will amount to £1.1 billion of economic benefits over the next 25 years.
The Environment Agency has been working on two key elements: placing rock armour along the sea wall and refurbishing four outfalls that drain water from the land into the estuary.
In 2024, large granite rocks were installed along 3km of the sea wall to absorb wave energy and significantly reduce the amount of water washing over the defences. This year, small gaps around pipelines have been filled, and access routes to the outfalls have been improved, making future maintenance and inspection possible.
The outfalls play a crucial role in reducing flood risk by allowing water to drain from all the land behind the defences into the Humber estuary.
Mark Adams, the Environment Agency’s local Client Lead for the project said:
“Another key milestone has been achieved to better protect local communities and businesses. Once fully completed next year, this project will better protect 2,400 properties from flooding for at least 25 years. Throughout our work we have been factoring in the challenges of climate change.”
Starting work on the scheme 1 year early in 2023 resulted in £5 million of savings, by avoiding inflated rock costs and securing temporary storage areas.
An additional year of work is required to complete the necessary construction. Next year, work will include a new overflow being installed at Oldfleet Drain, linking to Middle Drain pumping station, to further reduce flood risk upstream. Together with additional outfall resilience improvements elsewhere.
The number of properties which are currently better protected due to this work will rise from 2300 to 2400 when fully completed
“SAS (Surplus Activated Sludge) is a bit weird and
Owen Mace has taken over as Director of the British Plastics Federation (BPF) Plastic Pipes Group on the retirement of Caroline Ayres. He was previously Standards and Technical Manager for the group.
Hear how United Utilities is accelerating its investment to reduce spills from storm overflows across the Northwest.