Work by Tideway to connect the existing sewers into the new super sewer has reached a key milestone at Albert Embankment foreshore, following the breakthrough of a 30 metre tunnel under Vauxhall Bridge.

Once in operation, the 2.5 metre-diameter tunnel will take sewage from the Clapham sewer outfall, located upstream of Vauxhall Bridge, into an interception chamber and ultimately to the main tunnel of the super sewer.
The culvert is formed of 14 concrete pipes reinforced with stainless steel, pushed hydraulically into the ground, and took around two months to build.
Lee Fisher, project manager at Albert Embankment, said:
“This was a challenging pipejacking operation, taking place at a shallow depth under a busy part of London. The huge amount of preparation by the team included stabilising the ground and providing protection from the Thames’ tides, which allowed us to make good progress. Throughout this piece of work, we have utilised the river to deliver supplies and remove spoil, reducing the number of lorries on London’s roads.”
The shield and all the concrete pipes used to construct the tunnel was removed by river.
Other ongoing work includes a special ‘plunge pool’ under construction at Earl Pumping Station.

The 50 metre-deep shaft at Earl will connect the existing sewer network into the under-construction Greenwich Connection Tunnel, which will transfer sewage into the main super sewer at Chambers Wharf.
The shaft at Earl Pumping Station is an ‘online shaft’ – meaning it will drop directly into the Greenwich Connection Tunnel, instead of via a connection tunnel.
To facilitate the arrival of the Greenwich Connection Tunnel TBM Annie in the next few weeks, the shaft has been fully excavated and a base slab installed, before being partially backfilled with a temporary cement material into which the TBM will tunnel.
Above this, the shaft has been filled with water to match the external water pressure of five bar.
Brooke Knight, project manager at Earl Pumping Station, said:
“This is part of our preparation to welcome TBM Annie to Earl Pumping Station, as she digs the Greenwich Connection Tunnel. The 40 metre-deep pool of water will balance the ground pressure when TBM Annie tunnels underneath, allowing us to tunnel straight into the shaft.”
“At tunnelling depth, the ground conditions in this part of London can be challenging because of the large flints and possible fissures in the chalk, so tunnelling and shaft excavation had required a huge amount of preparation.”
Earl Pumping Station is part of an existing Thames Water Pumping Station that has been in use for many years and will remain operational throughout the works.
HUBER Technology UK & Ireland are inviting people to register for their March webinar where they will be providing information about HUBER water intake screens for municipal and industrial applications.

Hear how United Utilities is accelerating its investment to reduce spills from storm overflows across the Northwest.